Update
During change CHG0001058 engineers had an unexpected hardware failure that had to be resolved for change to proceed. In order to complete change the window is going to be extended 12 hours. Engineers have not seen any impact to our services, and do not expect to see any impact to our services in completing the change.
Posted Feb 13, 2020 - 17:34 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 12, 2020 - 03:01 UTC
Scheduled
SCHEDULED MAINTENANCE: US EAST (NA9) INFRASTRUCTURE MAINTENANCE

Impact: No impact to clients is expected

Dear Client

On the date listed below engineers will be performing scheduled maintenance in the location listed below. This maintenance is necessary to address known performance and stability issues within the storage infrastructure. During this maintenance we will be upgrading storage devices to the latest vendor approved and tested OS release. Although this type of maintenance has been performed in the past without impact, there is a low risk of latency and service disruption to Client Cloud Servers. The Admin UI/API and Community will remain available.

Change Reference Number: CHG0001058
US East: (NA9): Tuesday February 11th 07:00 PM US Pacific Standard Time (12/2 03:00 UTC)
Expected Total Duration: 42 Hours

Note this maintenance is specific only to the affected data center location and other Geographic Regions will continue to function normally.
Posted Jan 23, 2020 - 22:22 UTC
This scheduled maintenance affected: NA - US East (NTT Cloud NA9).