SCHEDULED MAINTENANCE: SINGAPORE (AP9,AP10) INFRASTRUCTURE MAINTENANCE
Scheduled Maintenance Report for NTT Ltd. Cloud
Completed
This Maintenance has been EXTENDED until 2000 UTC.

CHG0001180|RPA upgrade of SIN04 -RPA-CL1 & SIN01-RPA-CL1 Clusters. Zakeer is completed but this is a 2 part upgrade and the windows ends in 30 min.. 2nd part is CHG0001265 - Upgrading to SRM 8.1.x from SRM 6.1.2 in AP9 Sin04 and AP10 Sin01
Posted Feb 07, 2020 - 20:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 07, 2020 - 12:01 UTC
Scheduled
SCHEDULED MAINTENANCE: SINGAPORE (AP9,AP10) INFRASTRUCTURE MAINTENANCE

Impact: Disaster Recovery Services replication will pause multiple times during maintenance window.

Dear Client

On the date listed below engineers will be performing scheduled maintenance in the location listed below. This maintenance is necessary to perform upgrades to the storage infrastructure supporting the Disaster Recovery Services. Engineers will be upgrading storage devices to the latest vendor approved and tested OS release. During the maintenance window Disaster Recovery Replication Services will pause up to 8 times for up to 15 minutes each time. At completion of window engineers will monitor to make sure all replication services are in sync.

Change Reference Number: CHG0001180
Singapore (AP9,AP10): Friday February 7th 9:00 PM Tokyo (12:00 UTC)
Expected Total Duration: 6 Hours

Note this maintenance is specific only to the affected data center location and other Geographic Regions will continue to function normally.
Posted Feb 01, 2020 - 00:07 UTC
This scheduled maintenance affected: AP - Singapore (CSfS AP9).