SCHEDULED MAINTENANCE: FRANKFURT (EU6) CLOUD INFRASTRUCTURE MAINTENANCE
Scheduled Maintenance Report for NTT Ltd. Cloud
Completed
The scheduled maintenance has been completed.
Posted Feb 21, 2020 - 01:00 UTC
Update
Maintenance CHG0001160 has been paused due to unexpected hardware failure. Replacement part will be on site and replaced in next 24 hours. Once issue is resolved maintenance will resume. Currently there is no impact to clients.
Posted Feb 19, 2020 - 17:24 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 18, 2020 - 20:00 UTC
Scheduled
Impact: No impact to clients is expected

Dear Client

On the date listed below engineers will be performing scheduled maintenance in the location listed below. This maintenance is necessary to address known performance and stability issues within the storage infrastructure. During this maintenance we will be upgrading storage devices to the latest vendor approved and tested OS release. Although this type of maintenance has been performed in the past without impact, there is a low risk of latency and service disruption to Cloud Services.

Change Reference Number: CHG0001160
Frankfurt (EU6): Tuesday February 18th 09:00 PM Central European Time (20:00 UTC)
Expected Total Duration: 53 Hours

Note this maintenance is specific only to the affected data center location and other Geographic Regions will continue to function normally.
Posted Jan 29, 2020 - 23:08 UTC
This scheduled maintenance affected: EU - Germany (NTT Cloud EU6).