STANDARD MAINTENANCE: SINGAPORE (AP3,AP9,SIN01) CPNC INFRASTRUCTURE
Scheduled Maintenance Report for NTT Ltd. Cloud
Completed
The scheduled maintenance has been completed.
Posted Oct 18, 2019 - 15:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 18, 2019 - 12:00 UTC
Scheduled
Impact: During the maintenance clients with CPNC Site to Site VPN and Direct Connect Service without High Availability option will go down for 5 to 15 minutes.

Dear Client

On the date and time listed below engineers will be performing maintenance in the following cloud locations. This maintenance is necessary to perform vendor recommended IOS upgrade to network devices supporting the CPNC service. Current IOS is soon to be end of life. During the maintenance clients with CPNC Site to Site VPN and Direct Connect Service without High Availability option will go down for 5 to 15 minutes while the primary device reloads. Clients with High Availability may see brief latency during fail-over process.

Change Reference Number: CHM122639445
Singapore (AP3,AP9,SIN01): Friday October 18th 09:00 PM Japan Standard (12:00 UTC)
Expected Total Duration: 3 Hour

Note this maintenance is specific only to the affected data center locations and other Geographic Regions will continue to function normally.
Posted Oct 01, 2019 - 20:23 UTC
This scheduled maintenance affected: AP - Singapore (Managed Hosting SIN01, NTT Cloud AP3, CSfS AP9).