EMERGENCY MAINTENANCE: SYDNEY (ALL LOCATIONS) CPNC INFRASTRUCTURE
Scheduled Maintenance Report for NTT Ltd. Cloud
Completed
The scheduled maintenance has been completed.
Posted Sep 26, 2017 - 12:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 26, 2017 - 10:00 UTC
Scheduled
Dear Client

On the date and time listed below engineers will be performing maintenance in the following cloud locations. This maintenance is necessary to add capacity to CPNC devices in the cloud location below. No impact to client CPNC traffic is expected, however there is medium risk of brief latency and or packet loss for client traffic using our CPNC service.

Change Reference Number: CHM116142360

Sydney (All Locations): Friday September 26th 08:00 PM Australia Eastern Standard Time (10:00 UTC)

Expected Total Duration: 2 Hour

Note this maintenance is specific only to the affected data center locations and other Geographic Regions will continue to function normally.
Posted Sep 26, 2017 - 02:05 UTC
This scheduled maintenance affected: AU - Sydney (CPNC).