SCHEDULED MAINTENANCE: US EAST (NA9) CLOUD INFRASTRUCTURE MAINTENANCE
Scheduled Maintenance Report for NTT Ltd. Cloud
Completed
The scheduled maintenance has been completed.
Posted Jul 22, 2020 - 15:30 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 20, 2020 - 00:30 UTC
Scheduled
SCHEDULED MAINTENANCE: US EAST (NA9) CLOUD INFRASTRUCTURE MAINTENANCE

Impact: No impact to clients is expected

Dear Client

On the date listed below engineers will be performing scheduled maintenance in the location listed below. This maintenance is necessary to perform upgrades to the storage infrastructure supporting the Cloud Services. During this maintenance we will be upgrading storage devices to the latest vendor approved and tested OS release. Although this type of maintenance has been performed in the past without impact, there is a low risk of latency and service disruption to Client Cloud Servers. The Admin UI/API and Community will remain available.

Change Reference Number: CHG0004833
US East: (NA9): Sunday July 19th 05:30 PM US Pacific Standard Time 20/7 00:30 UTC)
Expected Total Duration: 63 Hours

Note this maintenance is specific only to the affected data center location and other Geographic Regions will continue to function normally.
Posted Jul 08, 2020 - 19:34 UTC
This scheduled maintenance affected: NA - US East (NTT Cloud NA9).