SCHEDULE MAINTENANCE: MELBOURNE (AU2) INFRASTRUCTURE
Scheduled Maintenance Report for NTT Ltd. Cloud
Completed
The scheduled maintenance has been completed.
Posted Nov 02, 2018 - 12:01 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 02, 2018 - 10:00 UTC
Scheduled
SCHEDULE MAINTENANCE: MELBOURNE (AU2) INFRASTRUCTURE

Impact: No impact to our clients is expected

Dear Client

On the date listed below engineers will be performing maintenance in the following locations. This maintenance is needed to perform decommission of unused network equipment supporting cloud services. During the maintenance engineers, will be removing unused devices from cloud network environment. This device is no longer required, no impact to client environments is expected.

Change Reference Number: CHM119625673
Melbourne (AU2): Friday November 2nd 09:00 PM Australia Eastern Daylight (10:00 UTC)
Expected Total Duration: 2 Hour

Note this maintenance is specific only to the affected data center locations and other Geographic Regions will continue to function normally.
Posted Nov 01, 2018 - 08:43 UTC