Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 21, 2017 - 11:00 UTC
Scheduled
Impact: No client impact expected
Dear Client
On the date listed below engineers will be performing maintenance in the location listed below. This maintenance is necessary to perform power audits in the location listed below. Although no changes are being made, engineers may have to physically trace cables, leading to low risk of accidental service disruption.
Change Reference Number: CHM114659792
Sydney (AU1,AU6,AU9): Friday April 21st 09:00 PM Australia Eastern Standard Time (11:00 UTC)
Expected Total Duration: 44 Hours
Note this maintenance is specific only to the affected data center location and other Geographic Regions will continue to function normally.
Posted Apr 10, 2017 - 15:05 UTC
This scheduled maintenance affected: AU - Sydney (NTT Cloud AU1, NTT Cloud AU6, NTT Cloud AU9, Cloud Monitoring, CPNC).