EMERGENCY MAINTENANCE: CANADA (CA1,CA2,YYZ01) NETWORK INFRASTRUCTURE
Scheduled Maintenance Report for NTT Ltd. Cloud
Completed
The scheduled maintenance has been completed.
Posted Aug 04, 2018 - 03:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 04, 2018 - 01:01 UTC
Scheduled
Impact: There is a high risk of brief packet loss and or latency during failover process, no more than 3 minutes.

Dear Client

Engineers have identified a potential issue with core routers in location listed below. Engineers will be performing changes to both primary and secondary devices in rolling fashion to address the issue and prevent unplanned outage. There is a high risk of brief packet loss and or latency during fail-over process, no more than 3 minutes.

Change Reference Number: CHM118856670
Canada: (CA1, CA2): Friday August 3rd 09:00 PM Eastern Daylight Time (4/8 01:00 UTC)
Expected Total Duration: 2 Hours

Note this maintenance is specific only to the affected data center location and other Geographic Regions will continue to function normally.
Posted Aug 02, 2018 - 21:29 UTC
This scheduled maintenance affected: CA - Canada (Managed Hosting YYZ01, NTT Cloud CA1, NTT Cloud CA2).