SCHEDULED MAINTENANCE: NEW ZEALAND (AU8,AU11) CPNC INFRASTRUCTURE
Scheduled Maintenance Report for NTT Ltd. Cloud
Completed
The scheduled maintenance has been completed.
Posted Nov 16, 2018 - 16:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 16, 2018 - 13:00 UTC
Scheduled
Impact: No impact to clients expected.

Dear Client

In preparation for future release of our cloud product, engineers will be standardizing SNAT/NAT network configurations for traffic destined for CPNC connections in the location listed below. These changes are not expected to cause any impact to client environments, however there is a medium risk that when change is applied, open network connections using CPNC service could reset. CPNC Cloud Customers are encouraged to run post change test of applications and report any unexpected issues to the NOC.

Change Reference Number: CHM119704220
New Zealand (AU8,AU11): Saturday November 17th 12:00 AM Australia Eastern Daylight (16/11 13:00 UTC)
Expected Total Duration: 3 Hours

Note this maintenance is specific only to the affected data center locations and other Geographic Regions will continue to function normally.
Posted Nov 09, 2018 - 00:02 UTC
This scheduled maintenance affected: AU - New Zealand (CPNC).